RI03: US Route 360

RI03 Overview Map

Fairfield Avenue TO Springdale Road

Survey

The survey regarding potential transportation safety, operations, congestion mitigation, capacity preservation and bicycle/pedestrian improvements along Route 360 (Mechanicsville Tpk.) between Fairfield Ave. and Springdale Rd. is complete.

Project Purpose

Project objectives are to address bicycle and pedestrian safety concerns and to conduct congestion mitigation and capacity preservation along the subject corridor. Two nodes and 17 segments were identifed as VTrans Priority 1 needs along the study corridor. Goals are to identify safety and capacity mitigation improvements to improve and preserve the safety and capcity of the corridor for all transportation users.

Study Partners

  • City of Richmond
  • Henrico County
  • GRTC Transit System
  • Richmond Regional Transportation Planning Organization

Key Points of Contact

District Lead: Liz McAdory 

Lead Consultant: Stuart Samberg 

Schedule

PHASE DATES TASKS
Phase 1 August 2021 – September 2021 Problem Diagnosis/Brainstorm Alternatives
Phase 2 October 2021 – March 2022 Stakeholder/Public engagement and feedback
Phase 3 March 2022 – July 2022 Investment strategy cost estimation and refinement

Last updated: March 7, 2024