RI01: US 60 - Semmes Avenue

RI01 Overview Map

From Route 683 (Forest Hill Avenue) TO US 1 / US 301 (Cowardin Avenue)

Survey

The survey regarding potential transportation safety, operations, transit, transportation demand management and bicycle/pedestrian improvements along Route 60 (Semmes Ave.) between Route 683 (Forest Hill Ave.) and Route 1/301 (Cowardin Ave.) is complete.

Project Purpose

The purpose of the project is to address the bicycle, pedestrian and vehicular safety concerns, bicycle access needs, and transit and travel demand management needs along the Route 60 study corridor. Two (2) VTrans Priority 2 segments were identified along the study corridor.

Study Partners

  • City of Richmond
  • GRTC Transit System
  • Richmond Regional Transportation Planning Organization

Key Points of Contact

District Lead: Liz McAdory

Lead Consultant: Jeff Kuttesch (RK&K)

Schedule

PHASE DATES TASKS
Phase 1 August 2021 – September 2021 Problem Diagnosis/Brainstorm Alternatives
Phase 2 October 2021 – March 2022 Stakeholder/Public engagement and feedback
Phase 3 March 2022 – July 2022 Investment strategy cost estimation and refinement

Last updated: March 7, 2024

Alert Icon

Please note that this file is not ADA compliant. Choose one of below options: