Bloomsbury Lane TO Woodland Drive
The Phase 2 survey regarding potential improvements on Route 208 (Courthouse Rd.) between Bloomsbury Ln. and Woodland Dr. in Spotsylvania is complete.
The purpose of this study is to compile and analyze data related to VTrans needs that have been identified along the corridor and to produce recommended improvements. Emphasis should be placed on the higher priority needs locations. Deliverables should include recommendations in the form of SMART SCALE-ready projects containing analytical documentation that fully support the recommended improvement(s).
District Lead: Linda LaSut and Casandra Lord
Lead Consultant: John Riley and Karzan Bahaaldin
PHASE | DATES | TASKS |
---|---|---|
Phase 1 | May - August 2023 | Diagnose Problems/Brainstorm Alternatives |
Phase 2 | September - December 2023 | Evaluate Preliminary Alternatives/Conduct Public Outreach and Obtain Feedback/Select Preferred Alternatives |
Phase 3 | January-July 2024 | Conduct Risk Assessment/Develop and Refine Preferred Alternatives/Prepare Cost Estimate and Investment Strategy |
Last updated: April 2, 2024